Particulars | Details/Status |
---|---|
Project Name | “Upgradation to Four Lane with paved Shoulder of NH-341from Bhimasar, Junction of NH-41 to Anjar – Bhuj upto Airport Junction, Km 0.000 to Km 65.478 in the State of Gujarat on Hybrid Annuity Mode):” |
NH No. (New/Old) | NH-34 |
Scheme/Phase | Bharatmala Pariyojana |
Mode of Execution | Hybrid Annuity Mode (HAM) |
Concessionaire Name | M/s GR Bhimasar Bhuj Highway Private Limited |
Date of Letter of Award (LOA) | 30.03.2022 |
Appointed Date | 02.01.2023 |
Construction Period (in Days) | 910 Days from the Appointed Date |
Schedule Completion Date | 29.06.2025 |
Operation & Maintenance Period | 15 years from PCOD / COD |
Independent Engineer | To be Appointed |
Authority Name | National Highways Authority of India, PIU-Gandhidham |
Independent Engineer Mobilization Date | To be mobilized |
No. of Lanes/ Configuration | 4 Lane |
Bid Project Cost | 1085 Cr. |
Total Length of the Project | 59.538 km |
Length of Bypasses (Name of Town) | 20.800 km (Anjar, Sapeda, Ratnal, Kukma) |
Length of Realignments Road | 3.7 Km |
No. of Flyovers | 0 nos. |
No. of ROB | 4 nos. |
No. of Underpasses, VUP | 09 nos. |
No. of Major Bridges | 02 nos. |
No. of Minor Bridges | 21 nos. |
No. of FOB | NIL |
No. of Culverts | Box Culvert – 30 Nos. – Reconstruction Box Culvert – 39 Nos. – New Construction Slab Culvert – 04 Nos. – Repair & Widening Slab Culvert – 28 Nos. – New Construction Slab Culvert – 01 Nos. – Reconstruction Hume Pipe Culvert- 26 Nos. – Repair & Widening |
Toll Plaza | 02 Nos. Ch-13+125 & 49+803 |