Salient Features

Salient Features of Project

Particulars Details/Status
Project Name “Upgradation to Four Lane with paved Shoulder of NH-341from Bhimasar, Junction of NH-41 to Anjar – Bhuj upto Airport Junction, Km 0.000 to Km 65.478 in the State of Gujarat on Hybrid Annuity Mode):”
NH No. (New/Old) NH-34
Scheme/Phase Bharatmala Pariyojana
Mode of Execution Hybrid Annuity Mode (HAM)
Concessionaire Name M/s GR Bhimasar Bhuj Highway Private Limited
Date of Letter of Award (LOA) 30.03.2022
Appointed Date 02.01.2023
Construction Period (in Days) 910 Days from the Appointed Date
Schedule Completion Date 29.06.2025
Operation & Maintenance Period 15 years from PCOD / COD
Independent Engineer To be Appointed
Authority Name National Highways Authority of India, PIU-Gandhidham
Independent Engineer Mobilization Date To be mobilized
No. of Lanes/ Configuration 4 Lane
Bid Project Cost 1085 Cr.
Total Length of the Project 59.538 km
Length of Bypasses (Name of Town) 20.800 km (Anjar, Sapeda, Ratnal, Kukma)
Length of Realignments Road 3.7 Km
No. of Flyovers 0 nos.
No. of ROB 4 nos.
No. of Underpasses, VUP 09 nos.
No. of Major Bridges 02 nos.
No. of Minor Bridges 21 nos.
No. of FOB NIL
No. of Culverts Box Culvert – 30 Nos. – Reconstruction
Box Culvert – 39 Nos. – New Construction
Slab Culvert – 04 Nos. – Repair & Widening
Slab Culvert – 28 Nos. – New Construction
Slab Culvert – 01 Nos. – Reconstruction
Hume Pipe Culvert- 26 Nos. – Repair & Widening
Toll Plaza 02 Nos. Ch-13+125 & 49+803