Items | % Weightage as per Annexure-I of Schedule - G | % Physical Progress (In Previous month) | % Physical Progress(Current month) | % Cumulative Physical Progress(C = A + B) |
---|---|---|---|---|
(A) |
(B) |
(C) |
||
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 46.97% |
39.47% |
1.06% |
40.53% |
Major Bridge Works & ROB/ RUB | 24.43% |
10.46% |
3.73% |
14.16% |
Structures (elevated sections, reinforces earth) | 11.78% |
11.78% |
0.00% |
11.78% |
Electrical and public health utilities | 1.34% |
1.33% |
0.00% |
1.33% |
Other Works | 15.48% |
9.22% |
0.68% |
9.90% |
Total | 100% |
72.26% |
5.48% |
77.71% |