Physical Progress

Physical Progress

Items % Weightage as per Annexure-I of Schedule - G % Physical Progress (In Previous month) % Physical Progress(Current month) % Cumulative Physical Progress(C = A + B)
(A)
(B)
(C)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads)
46.97%
39.47%
1.06%
40.53%
Major Bridge Works & ROB/ RUB
24.43%
10.46%
3.73%
14.16%
Structures (elevated sections, reinforces earth)
11.78%
11.78%
0.00%
11.78%
Electrical and public health utilities
1.34%
1.33%
0.00%
1.33%
Other Works
15.48%
9.22%
0.68%
9.90%
Total
100%
72.26%
5.48%
77.71%