Details of Right of Way Available/ Not Available

Details of Right of Way Available/ Not Available

S.No Chainage Hindrance Length Survey No. Hindrances Type Affected work Current Status As on 21.01.2025 Remarks
From To RHS LHS
1 07+750 07+800 50 - 512/1 Compound Wall Side Shoulder, Earthen Drain, Utility corridor Due to the Road Plan & Profile to accommodate road width up to toe additional land is required or alternatively the road design may be modified. Decision taken by the Authority.  
2 10+700 10+780 - 80 106 LA issue, Compound wall compensation pending service road, RCC Drain, Utility corridor Hissa Mapani report awaited from DILR and Structure Award payment also pending due to same.  
3 13+260 13+360 - 100 53 Land Acquisition Issue Earthen Drain, Utility corridor Affected person raised the dispute regarding Land area under Acquisition. The matter is pending at DILR for verification and final opinion. Payment pending.  
4 14+550 14+640 90 90 735/1 LA issue, Structure compensation pending MCW, Service Road, RCC Drain, Utility corridor Hissa Mapani report awaited from DILR. The whole land has been acquired but the same must be defined and devide for existing sub plots. Process Pending.  
5 19+040 19+260 220 220 588/3 LA issue, Hissa mapni issue & tree compensation pending MCW, Earthen Drain, Utility corridor At revenue Survey No. 558/3 missing plot and under course of 3G.  
6 22+920 23+060 140 140 409 LA issue, Missing plot MCW,  service road, RCC Drain, Utility corridor Missing Plots under course of 3G  
7 24+100 24+200 - 100 376/1 LA issue, Missing plot Service road, RCC Drain, Utility corridor Missing plots under course of 3G  
8 25+380 25+500 120 120 267/1 LA issue, Missing plot Service road, RCC Drain, Utility corridor Additionally, Earlier land handover in police protection as government land. Now person is claiming ownership having court decree, Case posted to Authority. (From CH: 25+380 to CH: 25+500).  
9 25+890 26+000 110 110 259 and 255 LA issue, Mapni issue  compensation pending Service road, RCC Drain, Utility corridor The payment not disbursed. The overlapping of acquired land with previous acquisition needs to be verified and certificed by the DILR. Process pending at DILR. The construction of Service Road is hindered.  
10 29+240 29+420 180 - 33/2, Plot 2 LA issue, Award pending MCW, Major Junction, Earthen Drain, Utility corridor Missing Plots under course of 3G  
11 36+080 36+200 120 120 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payment.  
12 36+380 36+410 30 30 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payment.  
13 36+410 36+500 90 90 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payment.  
14 36+500 37+940 1,440 1,440 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payment.  
15 37+940 38+660 720 720 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payments.  
16 39+080 39+400 320 320 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payment.  
17 39+400 39+600 200 200 As Per the JMS LA issue, Under Arbitration Chubdak village issue (Award rate difference) Earthen Drain, Utility corridor The Award declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village) pending with Collector, Bhuj. The dispute still pending for subsequent difference of payments.  
18 43+100 43+260 160 - 49 LA issue, Missing plot Shoulder, Earthen Drain, Utility corridor Missing Plot,  report awaited from DILR  
19 47+570 47+650 80 80 As Per the JMS LA issue, 3G Pending - Reldi Moti MCW,  service road, RCC Drain, Utility corridor Matter pertains to realignment section for the construction of ROB (CH: 48+640). The land acquisition process has been completed. Award declared. However, payment not disbursed due to dispute and resistance raised by the Landowners.  
20 47+650 48+900 1,250 1,250 As Per the JMS LA issue, 3G Pending - Reldi Moti MCW, ROB, service road, RCC Drain, Utility corridor Matter pertains to realignment section for the construction of ROB (CH: 48+640). The land acquisition process has been completed. Award declared. However, payment not disbursed due to dispute and resistance raised by the Landowners.  
21 48+900 48+960 60 60 As Per the JMS LA issue, 3G Pending - Reldi Moti MCW,  service road, RCC Drain, Utility corridor Matter pertains to realignment section for the construction of ROB (CH: 48+640). The land acquisition process has been completed. Award declared. However, payment not disbursed due to dispute and resistance raised by the Landowners.  
22 49+020 49+080 60 60 As Per the JMS LA issue, 3G Pending - Reldi Moti MCW,  service road, RCC Drain, Utility corridor The matter pertains to realignment section for the construction of ROB (CH: 48+640). The land acquisition process has been completed. Award declared. However, payment not disbursed due to dispute and resistance raised by the Landowners.  
23 60+680 60+830 150 150 Govt, Land Encroachment (Shops & Houses) Service road, RCC Drain, Utility corridor Local Encroachment  
24 61+110 61+740 - 630 Govt, Land Encroachment (Smarati Van) Service road, RCC Drain, Utility corridor Encroachment (Smarati Van)  
25 62+430 62+640 210 210 397/1 LA issue 397/1 ( 870 ) Plotting MCW, Service road, RCC Drain, Utility corridor At survey no. 397/1 has been acquired and  payment disbursed. However, part of land have encroachment. Further, the land record for verification not available, so part of land is cannot be taken in possession.  
26 63+310 63+900 590 590 488/1 and 539/1 LA issue, compensation pending MCW, Service road, RCC Drain, Utility corridor Measurement Issues pending At DILR  
27 64+760 64+880 120 - 601/1, 601/2 LA issue, compensation pending MCW, Earthen Drain, Utility corridor The ownership of the land changed several times during the process of acquisition. However, the revenue records are not updated. Therefore, the disbursement cannot be done. Possession in dispute.  
28 65+200 65+350 150 - 660/1 LA issue, compensation pending MCW Utility corridor 660/1 sub plotting in map of sub plotting is not available with Authority. due to DILR not being able to clarify land area and titles of land due to that compensation not disbursed yet by CALA.  
Total 6,660 6,910          

Detailed Scope of Work & Physical Progress by Component