| 1 | 07+750 | 07+800 | 50 | - | 512/1 | Compound Wall | Side Shoulder,    Earthen Drain, Utility corridor | Due to the Road    Plan & Profile to accommodate road width up to toe additional land is    required or alternatively the road design may be modified. Decision taken by    the Authority. |  | 
  
    | 2 | 10+700 | 10+780 | - | 80 | 106 | LA issue,    Compound wall compensation pending | service road, RCC    Drain, Utility corridor | Hissa Mapani    report awaited from DILR and Structure Award payment also pending due to    same. |  | 
  
    | 3 | 13+260 | 13+360 | - | 100 | 53 | Land Acquisition    Issue | Earthen Drain,    Utility corridor | Affected person    raised the dispute regarding Land area under Acquisition. The matter is    pending at DILR for verification and final opinion. Payment pending. |  | 
  
    | 4 | 14+550 | 14+640 | 90 | 90 | 735/1 | LA issue,    Structure compensation pending | MCW, Service    Road, RCC Drain, Utility corridor | Hissa Mapani    report awaited from DILR. The whole land has been acquired but the same must    be defined and devide for existing sub plots. Process Pending. |  | 
  
    | 5 | 19+040 | 19+260 | 220 | 220 | 588/3 | LA issue, Hissa    mapni issue & tree compensation pending | MCW, Earthen    Drain, Utility corridor | At revenue Survey    No. 558/3 missing plot and under course of 3G. |  | 
  
    | 6 | 22+920 | 23+060 | 140 | 140 | 409 | LA issue, Missing    plot | MCW,  service road, RCC Drain, Utility corridor | Missing Plots    under course of 3G |  | 
  
    | 7 | 24+100 | 24+200 | - | 100 | 376/1 | LA issue, Missing    plot | Service road, RCC    Drain, Utility corridor | Missing plots    under course of 3G |  | 
  
  
    | 8 | 25+380 | 25+500 | 120 | 120 | 267/1 | LA issue, Missing plot | Service road, RCC Drain, Utility    corridor | Additionally, Earlier land handover in police protection as    government land. Now person is claiming ownership having court decree, Case    posted to Authority. (From CH: 25+380 to CH: 25+500). |  | 
  
    | 9 | 25+890 | 26+000 | 110 | 110 | 259 and 255 | LA issue, Mapni    issue  compensation pending | Service road, RCC    Drain, Utility corridor | The payment not    disbursed. The overlapping of acquired land with previous acquisition needs    to be verified and certificed by the DILR. Process pending at DILR. The    construction of Service Road is hindered. |  | 
  
    | 10 | 29+240 | 29+420 | 180 | - | 33/2, Plot 2 | LA issue, Award    pending | MCW, Major    Junction, Earthen Drain, Utility corridor | Missing Plots    under course of 3G |  | 
  
    | 11 | 36+080 | 36+200 | 120 | 120 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payment. |  | 
  
    | 12 | 36+380 | 36+410 | 30 | 30 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payment. |  | 
  
    | 13 | 36+410 | 36+500 | 90 | 90 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payment. |  | 
  
    | 14 | 36+500 | 37+940 | 1,440 | 1,440 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payment. |  | 
  
    | 15 | 37+940 | 38+660 | 720 | 720 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payments. |  | 
  
    | 16 | 39+080 | 39+400 | 320 | 320 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payment. |  | 
  
    | 17 | 39+400 | 39+600 | 200 | 200 | As Per the JMS | LA issue, Under    Arbitration Chubdak village issue (Award rate difference) | Earthen Drain,    Utility corridor | The Award    declared by the CALA, Bhuj, challenged by affected persons. The  Arbitration matter (Chubdak village)    pending with Collector, Bhuj. The dispute still pending for subsequent    difference of payments. |  | 
  
    | 18 | 43+100 | 43+260 | 160 | - | 49 | LA issue, Missing    plot | Shoulder, Earthen    Drain, Utility corridor | Missing    Plot,  report awaited from DILR |  | 
  
    | 19 | 47+570 | 47+650 | 80 | 80 | As Per the JMS | LA issue, 3G    Pending - Reldi Moti | MCW,  service road, RCC Drain, Utility corridor | Matter pertains    to realignment section for the construction of ROB (CH: 48+640). The land    acquisition process has been completed. Award declared. However, payment not    disbursed due to dispute and resistance raised by the Landowners. |  | 
  
    | 20 | 47+650 | 48+900 | 1,250 | 1,250 | As Per the JMS | LA issue, 3G    Pending - Reldi Moti | MCW, ROB, service    road, RCC Drain, Utility corridor | Matter pertains    to realignment section for the construction of ROB (CH: 48+640). The land    acquisition process has been completed. Award declared. However, payment not    disbursed due to dispute and resistance raised by the Landowners. |  | 
  
    | 21 | 48+900 | 48+960 | 60 | 60 | As Per the JMS | LA issue, 3G    Pending - Reldi Moti | MCW,  service road, RCC Drain, Utility corridor | Matter pertains    to realignment section for the construction of ROB (CH: 48+640). The land    acquisition process has been completed. Award declared. However, payment not    disbursed due to dispute and resistance raised by the Landowners. |  | 
  
    | 22 | 49+020 | 49+080 | 60 | 60 | As Per the JMS | LA issue, 3G    Pending - Reldi Moti | MCW,  service road, RCC Drain, Utility corridor | The matter    pertains to realignment section for the construction of ROB (CH: 48+640). The    land acquisition process has been completed. Award declared. However, payment    not disbursed due to dispute and resistance raised by the Landowners. |  | 
  
    | 23 | 60+680 | 60+830 | 150 | 150 | Govt, Land | Encroachment    (Shops & Houses) | Service road, RCC    Drain, Utility corridor | Local    Encroachment |  | 
  
    | 24 | 61+110 | 61+740 | - | 630 | Govt, Land | Encroachment    (Smarati Van) | Service road, RCC    Drain, Utility corridor | Encroachment    (Smarati Van) |  | 
  
    | 25 | 62+430 | 62+640 | 210 | 210 | 397/1 | LA issue 397/1 (    870 ) Plotting | MCW, Service    road, RCC Drain, Utility corridor | At survey no.    397/1 has been acquired and  payment    disbursed. However, part of land have encroachment. Further, the land record    for verification not available, so part of land is cannot be taken in    possession. |  | 
  
    | 26 | 63+310 | 63+900 | 590 | 590 | 488/1 and 539/1 | LA issue,    compensation pending | MCW, Service    road, RCC Drain, Utility corridor | Measurement    Issues pending At DILR |  | 
  
    | 27 | 64+760 | 64+880 | 120 | - | 601/1, 601/2 | LA issue,    compensation pending | MCW, Earthen    Drain, Utility corridor | The ownership of    the land changed several times during the process of acquisition. However,    the revenue records are not updated. Therefore, the disbursement cannot be    done. Possession in dispute. |  | 
  
    | 28 | 65+200 | 65+350 | 150 | - | 660/1 | LA issue,    compensation pending | MCW Utility    corridor | 660/1 sub    plotting in map of sub plotting is not available with Authority. due to DILR    not being able to clarify land area and titles of land due to that    compensation not disbursed yet by CALA. |  | 
  
    | Total | 6,660 | 6,910 |  |  |  |  |  |