Project Milestone Status

Project Milestones Status

Project Milestone Description (Days from Appointed Date) Planned Actual Current Status
Physical Progress (%) Scheduled Date Physical Progress (%) Achieved Date
Project Milestone-I 180 20% 30-06-2023 20.06 % 07.09.2023 29.90 %
Project Milestone-II 400 35% 05-02-2024 35.18% 15.02.2024 37.91%
Project Milestone-III 650 75% 12-10-2024 75.03% 28.08.2024 77.71%
Schedule Completion Date 910 100% 29-06-2025      

Note: Concessionaire has achieved Project Milestone within 90day grace period from Schedule date as per provision of Clause and Concession Agreement.